JGL implements Oracle Primavera Cloud for integrated task management
INDUSTRY
Pharmaceutical industry, R&D
CHALLENGE
Lack of integral understanding of planning, dependencies and critical path due to fragmented and non-standardized use of Trello.
RESULT
Implementation of Oracle Primavera Cloud (OPC) provides structure, better planning insight and faster decision making.
KEY PRODUCTS.
Oracle Primavera Cloud (OPC)
35 users, one uniform way of working
Full overview of dependencies and KPI impact
All projects discussed within one meeting
"The bigger picture was missing. We did not have relationships between activities, could not calculate the critical path and did not see how changes at the operational level affected our KPIs."
Ines Nenadić
Program & Project Manager
"Trello was too agile for us. We were using it at a low operational level, but couldn't connect to the strategic level."
Ines Nenadić
Program & Project Manager
"Oracle Primavera Cloud makes people look not only at the task level, but also at the schedule as a whole and the effect on future activities and KPIs."
Ines Nenadić
Program & Project Manager
"At the operational level we work agile, but strategically much more according to the waterfall approach. We needed a solution that supports both levels."
Ines Nenadić
Program & Project Manager
"Suzanne and Ghislaine were very professional. They helped us understand how Primavera works and guided us in setting up the structure."
Ines Nenadić
Program & Project Manager
"Previously, our team meetings lasted an hour and a half and we still didn't get through all the projects. Now we discuss all projects within that same time."
Ines Nenadić
Program & Project Manager
"We have experienced very good support and commitment from Primaned. Compared to other software, the aftercare and support in particular stands out positively."
Ines Nenadić
Program & Project Manager
About JGL
JGL is a leading Croatian pharmaceutical company and a global player within the therapeutic areas of cold and flu, ophthalmology and dermatology. The company was founded more than 35 years ago and has since grown steadily thanks to continuous investments in research and development, production facilities and technology. In doing so, JGL has developed into a leading European manufacturer of sterile pharmaceutical forms.
With more than 1,450 employees and operations in 60 markets, JGL develops and supplies pharmaceutical products through structured and multidisciplinary Research and Development (R&D) processes. The portfolio includes more than 150 brands and 300 products tailored to international markets. Thus, JGL actively contributes to improving the health and well-being of people worldwide.
The challenge
As part of modernizing its project management approach, JGL introduced agile principles within the R&D environment and deployed Trello as a Kanban-based tool for iterative task management. This approach provided greater flexibility and better alignment at the team level, but proved less appropriate within the context of regulated pharmaceutical development. The combination of strict regulations, inherent uncertainty in R&D and a highly flexible agile setup led to limited insight into the overall project structure. Planning took place primarily at the operational level, making it difficult to maintain an integrated view of milestones, dependencies, lead times and priorities at the portfolio level.
"The bigger picture was missing. We didn't have relationships between activities, couldn't calculate the critical path and couldn't see how shifts at the operational level affected our KPIs." - Ines Nenadić, PMP, Project Coordinator R&D
It soon became clear that the limitations were not so much in Trello as a tool, but rather in the way it was applied within a complex R&D environment. While Trello offers capabilities for structuring work with epics, task hierarchies and dependencies, the large number of users involved made consistent planning and maintenance difficult. Without clear ownership and central direction, boards became difficult to standardize and align. Ensuring data quality and structure also required continuous attention, as even minor changes by multiple users could disrupt planning logic. As a result, the system did not provide enough reliable and coherent information for steering and decision-making.
"Trello was too agile for us. We were using it at a low operational level, but could not connect to the strategic level." - Ines Nenadić, PMP, Project Coordinator R&D
Differences in usage arose within teams. Some users were inactive, while others used their own methods. This led to divergent interpretations and declining data quality. Projects were difficult to compare with each other and the creation of uniform reports was time-consuming. In addition, licensing capacity was lost due to inactive or inconsistent use.
A total of about 35 R&D staff had access to Trello. JGL concluded that a new tool alone was not enough. An integrated approach with clear processes, clear roles and standardized definitions of activities was needed. A planned task had to have the same meaning everywhere so that data became comparable and usable.
The solution
To create structure and overview in a complex project environment, JGL engaged Primaned as a strategic partner in project management. Together we translated operational bottlenecks and growth objectives into a clear and future-proof roadmap.
On Primaned's advice, JGL chose Oracle Primavera Cloud (OPC) as the foundation for the project management environment. This software supports a hybrid working method in which classic waterfall planning is combined with agile elements such as tasks.
"At the operational level we work agile, but strategically much more according to the waterfall approach. We needed a solution that supports both levels." - Ines Nenadić, PMP, R&D Project Coordinator
Unlike Trello, which focuses primarily on lightweight task management, Oracle Primavera Cloud provides visibility into the entire project structure, including scheduling and responsibilities. This provides the overview needed in regimented and multidisciplinary R&D projects. OPC supports critical path analysis and allows task ownership and completion dates to be incorporated directly into planning. This aligns well with JGL's needs.
Primaned implemented the OPC environment with a strong focus on governance and reusable templates. Our consultants provided three days of customized training and guidance. In the process, the capabilities of OPC were translated into R&D practice, with room for JGL to make its own process choices.
"Suzanne and Ghislaine were very professional. They helped us understand how Primavera works and guided us in setting up the structure." - Ines Nenadić, PMP, R&D Project Coordinator
An important part of the approach was establishing a unified way of working and sharply defining activities and tasks. Joint agreements created more consistency in how tasks are modeled, providing the basis for better interpretation and reporting. Internal training reinforced skills and ownership. During sprints, teams were introduced to the OPC Task Module in a practical way. Because the involvement of the internal team was limited during implementation, extra emphasis was placed on knowledge transfer and securing a sustainable way of working.
The result
With implementation and training, JGL has laid a solid foundation for using OPC within R&D projects, although adoption is still evolving. OPC allows critical path analysis to provide insight into which activities determine lead time within a single current planning model. This helps JGL identify risks earlier and manage priorities in a more focused way.
"Previously, our team meetings lasted an hour and a half and we still didn't get through all the projects. Now we discuss all projects within that same time."
- Ines Nenadić, PMP, R&D Project Coordinator
The new way of working reinforces task ownership and the use of end dates. Decisions and actions are directly linked to planned tasks, reducing duplicate administration and improving data quality. By deliberately reducing detail, micromanagement is reduced and the focus is more on risks and decision moments. Decision making is faster and consultations deliver more value.
"Oracle Primavera Cloud makes people look not only at the task level, but also at the schedule as a whole and the effect on future activities and KPIs."
- Ines Nenadić, PMP, R&D Project Coordinator
Oracle Primavera Cloud's scheduling module aligns better with task modules than other software JGL previously used, although differences remain that require further process optimization. The focus shifts to KPIs and progress at the project level, rather than exclusively daily task management.
"We have experienced very good support and commitment from Primaned. Compared to other software, the aftercare and support in particular stands out positively."
- Ines Nenadić, PMP, R&D Project Coordinator
Expert advice and implementation for Project Controls software
Primaned is trusted throughout the market for delivering cutting-edge in project control. As a leading European reseller and implementation partner for PMWeb and Oracle Primavera, we offer a comprehensive portfolio of tools tailored to complex project environments. Discover our proven expertise in planning, risk management and construction management information systems.
Related case studies
Discover practical solutions and proven results from real projects in our Case Study Hub.
Dura Vermeer
Explore the success story of Dura Vermeer, the first construction company in the Netherlands to implement Oracle Primavera Cloud.
Zeiss
Discover how Carl Zeiss improves their Corporate Real Estate Management process by implementing PMWeb. Learn more about the results they achieved following this successful project in the case study.